SYSE.24:4.3.2 - Establish that the necessary conditions can coexist

Place prerequisite Work and simultaneous contributions in the relevant windows. Distinguish elapsed time from person-time, equipment occupancy, and a contractual response interval. A sequential interpretation step starts when usable observations and its other prerequisites are available, not when collection is commissioned. Work may overlap only when its inputs, state, and resource conditions permit overlap.

Overlay demand on shared people, test facilities, data preparation, environments, and provider capacity. Two branches can each fit their own estimate while requiring the same specialist during the only permitted outage. A proposed reserve must be available at the same time as the resources it complements. Include preparation, acceptance, correction, and consequential recovery where the selected estimates do not already include them; do not count the same burden twice.

Use OPS.10:4 or a suitable domain operating Method when capacity or service feasibility is load-bearing. Use a suitable result already available. If obtaining one is warranted, request the result the comparison needs, such as a finite schedule for the supplied readiness times and joint resources, an infeasibility bound, or a qualified service forecast. A required workload above the available capacity can exclude a plan. A total within capacity can still hide incompatible prerequisites, time windows or simultaneous needs. If claimants choose independently, establish which combinations the provider must accommodate and which information is available before it commits a resource. Use the returned result under its conditions and retain the operating authority separately.

The same reasoning applies to access and continued support. Equipment available on Monday is not usable for a Friday task if calibration expires on Thursday; an export permission that ends at termination may not allow the transition Work to finish. If a needed person or provider is unavailable, compare rescheduling, reserving the joint window, changing the division of Work, supplying equivalent qualified means, or changing the current commitment. Add the consequences of the repair to the whole arrangement. Do not silently move its deadline, acceptance condition, or another System’s protected Work.