C.2.4:13.2 - Plain plan, high articulation
The note At 14:00, Maintenance Team 2 will isolate Pump P-17, replace Seal S-4, and restore service only after Leak Test LT-9 passes uses ordinary language and little formal notation. It can still reach AE4: the planned actor, affected entity, ordered actions, time, and completion condition are explicit enough for the planning branch. It routes to A.15; the note describes planned actions, while A.15.1 governs any admitted Work occurrence. The note needs no relation repair merely to count as explicit.