SYSE.54:5 - Worked case: a promised kit that maintenance has withdrawn
A field-service team is redesigning its equipment-booking support. Dispatchers say a crew receives a kit when a booking is confirmed. Storekeepers distinguish a temporary hold from physical pickup. Maintenance can withdraw the kit after inspection. The workshop asks what the new support must promise and what it must do when a hold cannot be fulfilled. The following values are constructed design inputs.
Participants initially place “request submitted”, “booking confirmed” and “kit collected” in one row. A storekeeper asks whether “confirmed” means allocated or collected; maintenance asks where withdrawal appears. They split the wording into “hold accepted” and “pickup recorded”, add the external event “kit withdrawn”, and mark the reaction to withdrawal as a hot spot. This changes the proposed behaviour before any database or service is chosen.
For kit K7, hold H31 belongs to crew C2 until 10:00. The proposed rule permits at most one active assignment of K7. A catalogue display can be a minute old, so a dispatcher viewing “available” sends request hold; the reservation operation checks authoritative availability before accepting it. Its outcome can be hold accepted or hold refused. The displayed value cannot authorize the promise.
The crew’s pickup request must name H31. Acceptance requires H31 to be active and the acceptance time to be before 10:00 on the agreed reservation time basis. Accepted pickup changes the assignment from held to collected; the hold is no longer available for expiry release. At or after the deadline, pickup under H31 is refused even if the expiry worker has not run. Release expired hold checks that H31 is still active and its deadline has passed before releasing it. The group has now exposed a concurrency requirement: pickup and expiry must be decided against compatible authoritative state and time conditions. It records that requirement for the software design.
| Challenge | Expected behaviour in the proposed model | Consequence for design |
|---|---|---|
| A second crew requests K7 while H31 is active | Refuse that request or offer a different kit; do not promise the same assignment twice. | The acceptance operation must preserve the assignment invariant. |
| The deadline has passed but expiry processing has not run | Refuse pickup under H31; reconcile or release the expired hold. | Acceptance checks the deadline as well as the current status, with an agreed time basis. |
| Pickup has already been recorded when an expiry request is processed | Do not release the collected kit because of the old deadline. | Identify H31 and its current state; replay of a stale request must not reverse a completed pickup. |
| Maintenance withdraws K7 before pickup | Suspend fulfilment of the hold, inform the dispatcher and crew, and request a replacement decision. | External withdrawal needs an observable input and a responsible reaction; automatic success is unavailable. |
| The maintenance message arrives twice or late | Determine whether it concerns this kit and relevant interval; avoid repeating an irreversible response blindly. | Message identity, currentness and reconciliation need an implementation decision. |
The participants also ask what the crew sees while a replacement is unresolved. “Confirmed” would now be a false promise. They choose an explicit awaiting-replacement state and notice requiring the dispatcher to act. The model therefore changes the use concept, the information displayed and the work to be supported. A policy for which replacement is acceptable remains a domain decision.
The immediate result is the corrected account, these proposed acceptance conditions and two implementation
questions: atomic handling of assignment transitions, and reliable receipt and reconciliation of maintenance
changes. SYSE.2 uses the account to revise the linked use and system concept. SYSE.6:4.4.4 shows why the
reservation invariant can stay in one authoritative operation while other work is separated. Observations
of current depot practice and implementation tests can support claims about actual practice and implemented
behaviour; agreement on the proposed model cannot establish either by itself.
Changed condition. Suppose maintenance provides no timely notification, only a nightly export. The same visible event sequence no longer supports a firm real-time availability promise. Participants compare a pickup-time inspection, a qualified provisional reservation and a changed provider arrangement. They must change the promised behaviour or obtain a timely contribution; adding a queue box cannot supply missing knowledge. Still-valid meanings of hold, pickup and identity remain useful.
Unlike use. In a design-consultancy inquiry, a client and engineer negotiate scope, revisiting cost and options in arbitrary order. A conversational region with “proposal accepted”, “inquiry withdrawn” and “response deadline reached” as exits can expose the handover to scheduled work. Enumerating a fixed command for every conversation would misrepresent this use. If only one representative story is needed to understand who exchanges which work objects, Domain Storytelling may supply a smaller sufficient account.