OPS.8.1:4.1 - Choose the completion and release events separately
Name the service to be protected, its receiving result and relevant horizon or deadline. Retain the event from which the customer has been waiting. Then identify the event currently proposed to permit another start: an operation completes, the selected constraint consumes its next ready job, a job leaves a controlled loop, acceptance arrives, or the remaining workload falls below a limit.
For a count limit, identify what enters and leaves its population. For a replenishment signal, identify the activity and ready supply it serves. Define readiness for the next operation using OPS.8; future outputs need not already exist.
Ask what obligation or operating work survives the signal. Trace it to the resource that would perform it. A card may be returned when a job leaves one loop even though that job still contributes load to another resource or a later visit. Preserve those contributions in the comparison.