OPS.9:5.5 - Choose diagnostic effort for a changing production regime

The fixed five-job case in :5.2 needs durations, readiness and reserved calendars. Those inputs already prove that eight verifier-hours cannot supply ten required hours. A new continuous machine-state feed would not improve that conclusion. Reuse the bound and its feasible extension.

A recurring production service instead alternates its limiting behavior. The question is where movable qualified assistance could help accepted output in each regime. A competent event-history account identifies jobs, accepted outputs and losses, but its weekly totals do not distinguish the shifting intervals. The supplied instrumentation can recover complete active intervals for machines A and B using a specialist-confirmed active/passive definition, including how blocking, starvation and unavailable states are classified. That definition, synchronized times and observed interval ends are prerequisites; a generic “busy” field is insufficient.

In a small constructed diagnostic return, A’s complete active interval is 0–6 and B’s is 4–10, with no other active intervals in that ten-hour window. Both have six-hour durations. The active-period analysis returns A alone over 0–4, shared/shifting involvement over 4–6 and B alone over 6–10. Each is involved for six of ten hours; the two 60% figures include the same overlap and must not be normalized into a single winner. These are descriptive shares of this trace, not confidence levels or a forecast for next week.

The analyst needs two hours to qualify and align the existing events, three to implement and check the duration-based analysis, and fifteen minutes per shift to examine missing states and the operating return. These are supplied local effort estimates. They are worth comparing with the cost of a permanent one-machine intervention and with a simpler manual replay if shifts are rare. If the treatment decision calls for a probe, use the identified intervals to design a permitted test of assistance in the relevant regime. Inspect accepted output, quality and interference. Do not buy permanent extra A capacity from an equal weekly total or from the diagnostic label alone. A model-based sensitivity study becomes the stronger supplier when a proposed finite change alters both machines and their buffers; it must represent that coupling and the relevant regime, rather than extrapolate a local derivative into the whole investment effect.