OPS.9:5.4 - The first result and sustained output choose different changes

Three independent serial resources A, B and C take 3, 5 and 2 hours per job. Inputs are ready at 0; transfers are immediate; buffers and downstream acceptance do not restrict this constructed deterministic case. A job is accepted only after C. The first completion is at 10; subsequent completions are five hours apart, so the fifth is at 30.

Two qualified arrangements are available before the window. An upstream fixture reduces A to 2 hours, leaving 5 and 2 elsewhere. Alternatively, moving qualified assistance from C to B produces durations 3, 4 and 4. Each has supplied permission and preserves the same accepted result; the move’s slower C is part of its actual cost, not an omitted side effect.

ArrangementFirst accepted resultFifth accepted resultPreparation burden outside the service window
Current 3/5/21030none
Upstream fixture 2/5/2929two qualified staff-hours, with a reversible fixture change
Reassigned assistance 3/4/41127three staff-hours of preparation and a changed C assignment

For one accepted result due by 9, select the fixture if its preparation can actually be supplied without displacing protected work. It changes the deadline result although B still limits the sustained pace. If the receiving requirement changes to five results by 28, that fixture is insufficient and the reassigned arrangement supplies a feasible alternative. A financial ranking needs the comparative costs. When the durations, resources and arrivals are fixed by the stated conditions, the model can guarantee or exclude timely service. For a probability of service in a variable operation, identify what the feasible cases and any supported probability bounds establish.

Accumulated waits can make another noncapacity treatment useful. Add four evidenced 15-minute handoff waits before acceptance of the first current job: it now finishes at 11. A coordinated handoff arrangement that removes those four waits returns completion to 10 without changing B’s five-hour rate. If the required first-result deadline is 10 and the supplied coordination/cover burden is half a staff-hour outside the service window, this can be preferable to the two-hour fixture preparation. If a wait is instead required for a qualified acceptance observation, it is not removable by dispatch policy; retain it and redo the comparison. The useful intervention follows the actual path and permissible waits, not the label “nonconstraint.”