OPS.10.2:7 - Conformance Checklist

  • The completion event, waiting origin, deadlines and any optimization preference are explicit.
  • Required operations, precedence and partial resource occupations describe the work being planned.
  • Resource sharing, capability, calendars and interruption conditions are jointly respected.
  • A claimed feasible result includes an executable assignment of the required work.
  • An impossibility or optimality conclusion has the necessary bound or complete-search basis.
  • Float, feasible postponement windows and final margin retain their target and resource-order conditions.
  • Protection has a named event, burden and delay basis, and the protected plan remains feasible.
  • Revision follows shared-resource competition as well as precedence and preserves completed facts.