OPS.10.2:8 - Common Anti-Patterns and How to Avoid Them
| Mistake | Consequence | Repair |
| Schedule each department’s copy of one person independently | The plan double-books the actual person. | Constrain that person’s combined occupied intervals. |
| Keep the first priority rule after it misses a date | A poor sequence is presented as an impossible commitment. | Reconsider permitted orders or obtain an impossibility argument. |
| Spend each task’s float independently | Several tasks consume the same delivery margin. | Recompute their joint postponement. |
| Treat the original critical sequence as permanent | New resource competition or delay is missed. | Recalculate conditional criticality from the changed arrangement. |
| Deduct closed hours while allowing a continuous task to span them | A nominal working-time calculation produces an impossible operation. | Place the complete required occupation in a permitted window. |
| Add a buffer without rescheduling its feeders | Earlier work competes with existing reservations. | Check the full protected assignment. |