OPS.10.2:8 - Common Anti-Patterns and How to Avoid Them

MistakeConsequenceRepair
Schedule each department’s copy of one person independentlyThe plan double-books the actual person.Constrain that person’s combined occupied intervals.
Keep the first priority rule after it misses a dateA poor sequence is presented as an impossible commitment.Reconsider permitted orders or obtain an impossibility argument.
Spend each task’s float independentlySeveral tasks consume the same delivery margin.Recompute their joint postponement.
Treat the original critical sequence as permanentNew resource competition or delay is missed.Recalculate conditional criticality from the changed arrangement.
Deduct closed hours while allowing a continuous task to span themA nominal working-time calculation produces an impossible operation.Place the complete required occupation in a permitted window.
Add a buffer without rescheduling its feedersEarlier work competes with existing reservations.Check the full protected assignment.