OPS.8.1:7 - Conformance Checklist
- The receiving result, its time requirement and the proposed release event are distinguishable.
- Known remaining operations and possible returns retain their resource use, readiness and customer waiting origin.
- Any claimed protection states its scenario, bounded family or probability interpretation; an unresolved risk remains visible in the release choice.
- A total-load screen is followed by placement when calendars, precedence or uninterrupted work can change feasibility.
- Feedback replaces or releases the relevant allowance; it does not count the same return twice.
- The selected rule states what happens to both returning work and the next candidate, including conflicts that need a changed priority or commitment.
- A changed feedback time or return route can reopen the decision.